Mersey Gateway

Cheshire

The Problem
  • A former experimental chemical works with a legacy of chlorinated solvent contamination
  • Site investigation recorded dissolved phase concentrations indicative of the presence of DNAPL
  • Site scheduled for redevelopment as part of the second Mersey Crossing
  • Sufficient remediation required to demonstrate betterment of site

The Solution

  • Treatment train approach to maximise contaminant mass recovery
  • Multi-Phase Extraction and aggressive DNAPL pumping to recover mobile NAPL
  • Groundwater re-injection to manage DNAPL flowpaths
  • CO2 injection used to enhance recovery of vapour phase contaminants
  • In-Situ Chemical Oxidation using Hydrogen Peroxide to address dissolved phase

The Result

  • 17t of chlorinated solvent contaminated mass recovered including over 2t of mobile DNAPL 
  • Significant reductions in dissolve phase concentrations following chemical oxidation
  • Agreement with the regulators that ‘betterment’ had been achieved
  • works completed within available programme prior to bridge construction

We Provide the Best Service in the Industry​

Unit 8, Commerce Park, Brunel Road, Theale, READING, RG7 4AB

Columbus House, Village Way, Tongwynlais, CARDIFF, CF15 7NE

 Chadwick House, Birchwood Park, Risley, WARRINGTON, WA3 6AE

 

© 2025 Biogenie Remediation UK Limited

Arrange a call back